2026-05-14 Phase 0 · bench build · 3 people
May 2026 — Where we are
Already concrete
- Costed procurement tracker; ~80% of Phase 1 P0 parts ordered
- Browser viewer with two georeferenced park sites
- Simulation + Gazebo SIL setup
- First sustained perception benchmark on bare Pi 5 1 GB
- Site-class business model in the operational docs
Still to prove
- Physical pickup on a real piece of trash
- Bounded route demo with before/after proof
- Field-condition thermal envelope (summer enclosure)
- Operator handoff UX for low-confidence detections
- Repeatable economics on a real recurring corridor
What worked this month
- First sustained perception benchmark on a bare Pi 5 1 GB —
1 hour, 7,649 inferences, 0 throttle, 0.05 % drift, 73.6 °C peak.
Latency budget for safety planning: ~220 ms per inference.
- Procurement closed on a usable parts list for Phase 1 build.
What didn’t
- Bench Pi 5 originally ran undervolted off a laptop USB-C cable;
benchmarks dropped Wi-Fi during inference. Fixed with a proper 27 W PSU.
- Original front caster SKU returned a 404 at order time; rerouted to
Service Caster direct.
Next 30 days
- First chassis assembly
- Add accuracy (mAP) measurement to the benchmark harness
- Stand up the Trash Trail API + minimal PWA